Genesee County Planning Board members Thursday night, on their way to approving the site plan for the Plug Power Inc., green hydrogen facility at the Western New York Science & Technology Advanced Manufacturing Park in the Town of Alabama, were on the receiving end of an education about the company’s operation from its vice president of project development.
Plug Power, a publicly traded business based in Latham (outside of Albany), is primed to become the first tenant at STAMP – with plans to put up an 8,000-square-foot operations and maintenance building, a 40,000-square-foot electrolyzer building and a 68,000-square-foot compressor building on the Crosby Road tech park.
The company is the world’s largest producer of hydrogen fuel cells that power forklifts and heavy-duty freight and its facility to be located at STAMP will be the largest in North America.
“This is the largest green hydrogen facility in North America by a lot,” Brenor Brophy said. “It actually is the largest green liquid hydrogen facility in the world. So, it is a major step forward in the energy transition from fossil fuels to renewable energy.”
Brophy took planners through the process of taking fresh water and electricity and turning that into hydrogen and oxygen. Plug Power had been making hydrogen cells for the warehouse and logistics industry and, last year, started making its own hydrogen.
“This is a green hydrogen product; fuel that is made from zero-carbon renewable energy,” Brophy said. “This is the hydroelectric energy from Niagara …”
He said Plug Power will harness renewable energy from the new substation that the company is building on the STAMP site – a facility that is large enough to power their entire park.
“We will take about half of that energy for our facility,” he said. “We take fresh water and electricity and we split it into hydrogen and oxygen. The only emission we have from this site is pure oxygen. We take that hydrogen gas and we cool it down to what I call biogenic temperature that turns it into a liquid.”
From there, tanker trucks will transport the liquid hydrogen to Plug Power customers all over the Northeast region.
Brophy said the firm’s customers include Walmart, Kroger’s, Amazon, Home Depot and Lowe’s.
He said the plant will produce 45 metric tons of hydrogen per day, with each truck holding about four and a half metric tons.
“So that means there will be approximately 10 trucks per day on average,” he said. “Not every truck is full leaving or (it could be) empty coming back, so it may be 10 to 12 trucks per day, which is quite low.”
Brophy called it a “beautiful site” on 30 acres. He said plans call for the placement of a row of trees along the front to obscure it from the road.
“It is a very important site,” he said. “We are absolutely delighted to be siting it in Western New York as a New York company. This is our first and biggest green hydrogen plant in what will be a national network.”
Planner Tom Schubmehl, who abstained from voting, was prepared with a list of questions about the project that focused on the following:
- Start-up Date
Brophy said he expects “to finish commissioning” in late 2022 or early 2023.
- Wastewater
Brophy said there are two components – the sanitary sewer needed for employees on site and discharge of leftover process water.
He said the number of employees on site is not large enough to support the construction of an actual wastewater treatment facility “so we will have a tank system there that will be approved by the DEC that we will have emptied out until such time as the wastewater treatment plant will require construction.”
“As far as what we call the process water … we will have the forced main that will discharge directly into Oak Orchard Creek and will require a permit from the (New York State) DEC (Department of Environmental Conservation).
- Stormwater
Brophy said a stormwater retention pond is an allowable use in that area.
- Reconstruction of Crosby Road
This will be done by the Genesee County Economic Development Center – a complete rebuild of the section from Stamp Drive south to the edge of Plug Power’s site. Also, a 12-inch water transmission main will be extended from Route 77 where it currently exists, down Stamp Drive and down Crosby Road to get to the Plug Power site.
- Tanker Trucks (noting there is parking for 26)
Brophy said those parked in the staging area will be empty so “when a driver shows up with an empty tanker we will have a full one waiting for them.”
- Storage Steer
Brophy said that storage unit will hold a week of production.
“It’s a high-resilience network,” he said. “If one goes down, we can support other plants in the network from that. Our customers are folks like Walmart, Kroger or Amazon, and so we can never let that warehouse go down. Amazon can’t go down a week before Christmas so we aim for a really high-resilience network.”
- Water Usage (noting the facility will use 280,000 gallons per day)
Schubmehl mentioned that Genesee County is calling for residents to conserve water this summer.
Mark Masse, GCEDC senior vice president of operations, said there is capacity coming up the line from Pembroke and County Engineer Tim Hens has “put place markers in for projects and Plug Power’s project has been held in the county water, so to speak, as a placeholder for a couple of years now. So, it has been accounted for and is included in those numbers.”
He added that GCEDC is pursuing another water line from Niagara County that could bring in an additional 1.5 million gallons per day.
“But the 280,000 gallons … that has been reserved in capacity in all of the numbers that Tim has been working with,” he reiterated.
Schubmehl responded that he was puzzled by that strategy.
“I just hope that you understand how difficult that is to know that this is what has been held in reserve while county residents are being told not to water their lawns this week,” he said. “It just seems a little odd.”