The Genesee County Legislature is expected to vote next week on two resolutions proposed by County Manager Matt Landers that would extend contracts with the architectural and construction management companies involved with the new $70 million county jail project.
The legislature’s Ways & Means Committee (today) and Public Service Committee (on Monday) approved extending the construction timeline with The Pike Company of Rochester from 18 to 20 months, based on the current market and supply chain constraints.
Landers said the specific start date hasn’t been set yet, but when it does it will be for 20 months – fitting into the June 1, 2022 through April 30, 2024 time period.
Since time is money, the extension will result in an increase of $121,298, with almost $96,550 of that for Pike to manage the extra two months of the construction time frame, Landers said.
“The remainder is cost escalation for Pike’s rising costs from delaying this project so long,” he added.
The other resolution is for two one-year renewals of the contract with SMRT Architects and Engineers of Latham, stretching out the agreement through February 2024. In this case, there is no additional cost to extend the pact.
The full legislature will convene at 5:30 p.m. next Wednesday.
Landers said that construction bid packages were released on Feb. 8. Bid awards are expected to go out in March with groundbreaking of the 184-bed jail on West Main Street Road scheduled for April.